Galveston County is moving toward state flood funding for Clear Creek and Dickinson Bayou while advancing the Clear Lake bridge replacement.
The Nov. 23 Commissioners Court special meeting agenda listed three consent items with direct ties to the Clear Lake area. No confirmed vote results were available in county records as of Nov. 24.
Flood project resolution
One item called for approval of a resolution supporting state funding for the Lower Clear Creek and Dickinson Bayou flood risk management project. The County Judge submitted the item.
Friendswood is listed as a planning partner in the broader effort. According to a League City project page, League City leads the Lower Clear Creek and Dickinson Bayou Regional Watershed Feasibility Study with a consortium that includes Galveston County, the City of Friendswood, the Harris County Flood Control District, the Texas Water Development Board, the Dickinson Bayou Watershed Steering Committee and the U.S. Army Corps of Engineers. An initial study was submitted to Congress in 2022 and authorized in the Water Resources Development Act of 2022. The consortium's stated goal is to secure congressional appropriation for pre-construction engineering and design as part of the WRDA 2030 cycle.
Bridge items
Two consent agenda items involved bridge work near Clear Lake.
One would authorize the County Judge to execute an engineering agreement with HDR Engineering for the Clear Lake Bridge Replacement project. The County Engineer submitted that item.
The second requested a fund transfer within the Unlimited Tax Road Bonds 2019 Fund to cover professional engineering services for the Clear Lake Road Bridge project. Neither item listed a dollar amount in the available agenda records.