Families of the approximately 464 students displaced from Westwood Elementary got a familiar message in an Aug. 9 letter: the district still expects to welcome kids back Monday, Aug. 24, but only if environmental testing gives the all-clear.
Friendswood ISD's third parent communication since the mold crisis began reconfirmed the target date while remediation work continues inside the 59-year-old campus. The reopening hinges on qualified third-party environmental professionals confirming the building is safe for occupancy, according to CW39.
The district described the Monday, Aug. 24, date as an estimate based on current progress, not a guarantee.
What still has to happen
Before the doors open, the district must finish two major repair projects: full replacement of the HVAC units that couldn't manage summer humidity and replacement of the roof over affected areas. Remediation contractor Texas General Contractors has already completed a comprehensive cleaning of the entire building, including the air duct system.
As of the district's Aug. 7 update, crews are also replacing carpeting throughout the campus. Once all physical work wraps, third-party environmental professionals must confirm mold levels have returned to safe thresholds.
What happens if the date slips
Friendswood ISD has not publicly announced a fallback plan. As we reported Aug. 6, students will not be relocated to another campus. They remain home on an extended summer break until clearance comes.
The rest of Friendswood ISD's six campuses opened as scheduled Tuesday, Aug. 18, meaning Westwood's PreK through second-grade students are starting the school year at least six days behind their peers if the Aug. 24 date holds.
How the crisis started
A failing HVAC system that couldn't handle summer humidity caused the mold outbreak. Third-party testing in July found elevated mold levels in air and surface samples, though no black mold was identified. The Friendswood ISD Board of Trustees voted 6-0 on Aug. 5 to authorize Superintendent Thad Roher to execute all agreements and approve expenditures for the emergency remediation. Trustee Tony Hopkins made the motion, seconded by Trustee Rebecca Hillenburg.
The crisis arrived three months after district voters narrowly rejected Proposition B in May, a $40.6 million bond measure that would have funded a replacement campus for Westwood, the district's oldest elementary school, built in 1967. Voters did approve Proposition A, a $26 million bond for districtwide infrastructure and maintenance.
In its initial Aug. 5 letter to families, the district wrote: "The safety of our students and staff must come before any timeline."
What's next
The district has pledged to update Westwood families every two days, or sooner if important new information becomes available. Kinder Camp, the orientation program for incoming kindergartners, remains postponed with no new date announced.
The total cost of the emergency remediation has not been publicly disclosed.